Monitoring Solution Providers Pte Ltd (MSP) was engaged by Taisei Corporation for monitoring the movement of surrounding buildings near their project site for Circle Line Stage 3 Contract 853, Construction and Completion of Marymount Station Including Tunnels. There were two total stations deployed for this project with one located on the roof of Lip Hing Industrial Building and another on the roof of Bishan 8 Condominium Tower A.
The Automated Monitoring System located at Lip Hing Industrial Building was for the structural monitoring of terrace houses along the tunnel route for LTA project C853. The terrace houses are situated along the proposed C853 Marymount MRT tunnel, in particular, the Pemimpin Place area and along Pemimpin Terrace. The total station for monitoring these houses was located on the roof of Lip Hing Industrial Building.